The following is a partial list of representative Bridge
Rehabilitation or Replacement design projects completed by Bayside
over the past 10 years.
 |
F-04-12 Route 202 over North Nashua River,
Fitchburg, MA
This three span structure consisted of rehabilitation of the superstructure
and replacement of the south span with prestress concrete boxes.
Rehabilitation of the existing northerly span trusses was done and
the structure retrofitted for seismic forces. The independent
spans were made seismically integral with the horizontal links.
Date Completed: 1998. |
S-10-20, Route 7A over Konkapot River, Sheffield,
MA
This bridge, currently under design, will replace a structurally deficient
structure. The new structure will consist of a 142’0” single span longitudinal,
curved girder superstructure. This superstructure will minimize
construction time and any environmental impacts. This section of
Konkapot River is mapped endangered species habitat and is known to have
high levels of mercury contamination. The substructure will consist
of concrete stub abutments founded upon ledge. Est. Construction:
2001 - 2002.
D-12-7=W-12-5, Oxford Avenue over French River,
Dudley/Webster, MA
A new superstructure was designed to increase both pedestrian and vehicular
safety. Two 14"0" travel lanes and two 5"9" sidewalls will be constructed
over longitudinal steel stringers. These stringers are supported on in
integral abutments. This superstructure directly ties into future maintenance
and deterioration is minimized due to two types of conditions. The integral
abutments are supported by driven steel H piles. Date completed:
1998.
One Mile Long Viaduct Section
of Route I-91, Downtown Springfield, MA
The rehabilitation involved six bridge structures, S-24-61-1, S-24-61-2,
S-24-61A, S-24-61B, S-24-83 and S-24-84. The rehabilitation was comprised
of five major components: bridge coping, expansion joints, and bridge
drainage, substructure repairs and electrical system. The bridge
coping was replaced to upgrade the traffic safety of the bridge and
involved partial deck replacement. The expansion joint repairs
involved replacing the existing joints with new strip seal expansion
joints and ride over joints. |
|
The bridge drainage rehabilitation included complete replacement of clearances
and tie in to the existing street drainage system below the viaduct.
Replacement of the electrical system was incorporated into the project due
to the poor existing condition of the system and involved replacing conduit,
wire junction boxes and the resetting of each light standard with new wiring,
luminaries and bulbs. Completion Date: 1997 (A Partnering Project)
Route 66 (Northampton to Easthampton), Northampton,
MA
The three bridge rehabilitation and widenings included in this project
consisted of a one span integrate abutment (N-19-38) supporting a prestress
plank bridge. The second bridge consisted of single span concrete box
(N-19-41) supported directly on stub abutments keyed into rock.
The third structure (N-19-21) consisted of a two span concrete arch, which
was rehabilitated for seismic loads. The arches were modeled in STAAD
and resultant seismic forces analyzed in a two-dimensional system.
Date Completed: Design Completed 1999, not yet Constructed.
 |
Route 202 over Connecticut River
(Sergeant Mueller Bridge)
Holyoke / South Hadley, MA
The 1700-foot, 7 span structure, consisted of the investigation of
a rehabilitation vs. reconstruction. The entire deck was replaced
and state-of the-art seismic isolators bearing were added in the rehabilitation
design to reduce earthquake forces on the structure. Bayside
also provided the design for a new pedestrian path way along the bridge
which was non existent on the standing structure. Date Completed:
1998 |
T-07-005 Old Turnpike Road over Squannacook
River, Townsend, MA
This project consisted of replacing a two span timber deck structure spanning
the Squannacook River. The existing structure was scour critical
with underlying of the southeast corner of the easterly abutment.
The proposed structure consisted of a single span (pre-stressed box beams)
structure built on abutments supported by steel piles which eliminated
scour critical element of the bridge. Date Completed: Fall 2000
Summer Street over Reserved Channel, Boston,
MA
This new bridge replacement structure design for the City of Boston consists
of an eighteen span continuous prestress deck structures supported by
concrete pier bents on driven and drilled concrete caissons. The span
length is 1,100 feet with over 121 caissons required. Bayside also
incorporated a fishing pier into the design. Permitting included;
water quality certification for disturbance and removal of contaminated
sediments; U.S. Coast Guard Bridge Permit; Coastal Zone Management (CZM)
Consistency Certification; U.S. Army Corps of Engineers; and Section 106,
Section 4(f) and HAER documentation for demolition of the existing National
Historic Register eligible bridge. Est. Date Completed: 2001
Hatches Harbor Dike,
Provincetown, MA
Hatches Harbor Dike is located near the airport in Provincetown, Cape
Cod, MA. The existing structure was an earthen dike lined with amour
stone on both sides. The existing single 24-inch pipe allows tide
water to pass through. The new structure is constructed of pre-casted
concrete box culverts with four 4’x7’ openings and concrete wing walls.
The size of each opening can be adjusted by opening or closing the
vertical gates. The purpose of the adjustable gates is to allow a
desirable amount of tide water to feed the salt march and also to
protect the airport during heavy storms. Date Completed: 1998 |
|
Cooks Dam Bridges (Main Street) over Mill River,
Northampton, MA
This project involved rehabilitation to two bridge structures for the
City of Northampton: a 66' concrete arch structure and a 29' span steel
stringer bridge. The steel stringer bridge was upgraded to HS-20
loading and thus eliminated the need to post the bridge for reduced loadings.
Areas of spalled and deteriorated concrete to the concrete arch structure
and the substructure elements were repaved. Provisions were included
for support of a new 8" water main across the structures new metal bridge
railings (Type G-3) were installed across the bridges and on the approaches.
The bridges are located within a historic mill site; therefore, particular
attention was given to the aesthetic impact of the bridge reconstruction
on the surrounding area. Date Completed: 1996
Route 202 (Winchester Road) over B&M Railroad,
Templeton, MA
This project involved complete replacement of a deficient bridge structure
with a new 3 span continuous steel stringer bridge. The depth of
the proposed superstructure was minimized and the roadway profile raised
to provide an increase of 3 additional feet of clearance over the railroad
tracks (21'-0") to allow passage of "double stack" railroad cars.
The proposed superstructure consists of an 81'-6" main span with 52'-3"
end spans. The bridge is constructed of unpainted, high strength,
weathering steel. The bridge provides a 40'-0" wide roadway with
one 7'-0" wide sidewalk. Concrete barrier rails and safety
screening, which meet the federal standards for crash testing were provided
on both sides.
New drilled caisson piers were constructed adjacent to the existing piers
in order to avoid impacts to train traffic and minimize need for sheeting.
The existing pier footings were retained for use in supporting crash walls
in front of the proposed piers. The caissons also provided necessary
flexibility to carry the required seismic forces with both piers being
"fixed" to the superstructure. The abutment foundations are stub
abutments supported on steel piles driven directly behind the existing
concrete abutments. The bridge was designed to be built in two stages
with two lanes of traffic to be maintained throughout the construction
period. Temporary traffic signals were provided during stage I to
provide an one-way reversible traffic flow across the structure.
Date Completed: 1997
Walworth Street over MBTA & Bay Colony Railroads,
Boston, MA
This project involved replacement of deficient steel stringer and timber
deck superstructure with prestressed concrete deck beams. The existing
concrete abutments were repaired and retained the proposed construction.
Pedestrian traffic was maintained throughout the construction period.
Date Completed: 1997
 |
Danvers Road over MBTA and B&M
Railroads, Swampscott, MA
Complete replacement of an existing bridge on an improved roadway
alignment. The new super- structure consists of prestressed
concrete butted deck beams supported on reinforced concrete abutments.
The new bridge has a 40' roadway width plus one sidewalk. Date
Completed: 1996 |
Center Bridge Road over Nashua River, Lancaster, MA
The existing bridge consists of a two span continuous steel stringer bridge.
The project, completed for the Town of Lancaster, involved complete replacement
of the concrete deck, widening of the roadway from 24 feet to 30 feet,
and seismic retrofitting to meet the present AASHTO seismic design requirements.
In addition, the load capacity of the structure is being increased to
HS-20 loading, which will eliminate the current need to post the bridge.
The roadway deck joints were eliminated on the rehabilitated structure
to minimize future maintenance requirements. The bridge railing
was upgraded to metal railing, Type S3-PL2, which meets current AASHTO
crash test criteria. Date Completed: 1995
South Union Street over B&M Railroad and
MBTA Tracks (L-4-22), Lawrence, MA
This project involved the complete replacement of the existing superstructure
and substructure at the same location. The new structure consists
of a single 105 foot long span utilizing 50" deep welded steel plate girders
and supported by new concrete counterfort abutments. Bayside's work
included a structural survey and inspection of the existing structure,
type study report, sketch plans submission, soils and foundation report,
and preparation of final plans, specifications and cost estimates.
Date Completed: 1996
Cummins Highway over Penn Central Railroad,
Boston, MA
This project involved complete replacement of the existing superstructure
with new prestressed concrete butted box beams. The existing granite
masonry abutments were modified and retained in the new construction.
Date Completed: 1994
S. Union Street over B&M
Railroad and MBTA (L-4-23), Lawrence, MA
This project involves the complete replacement of the existing structural
deficient superstructure of this two span structure. The existing
granite masonry abutment and piers were retained in the proposed reconstruction
and were modified in order to meet present AASHTO design criteria.
The new superstructure consists of two span continuous rolled stringers
with a concrete deck. Bayside's scope of work on this project
was identical to Bridge L-4-22 and included all work from initial
structural survey to the preparation of final plans, specifications
and cost estimates. Date Completed: May 1995 |
|
Water Street over Blackstone River, Millbury, MA
This project involved the rehabilitation of a two span steel stringer
bridge for the Town of Millbury. The bridge carries Water Street
over the Blackstone River and provides the only access to the Town's cemetery.
This project was initiated due to an undermining problem, which had developed
at the downstream end of the bridge pier. Our design included tremie
concrete fill to alleviate the undermining, as well as the complete replacement
of the concrete deck and repainting of the steel stringers. The
project is presently on hold and is waiting funding for construction.
Reconstruction of Route 2, Harvard to Acton, MA
This project involves 9.5 miles of highway improvements and the rehabilitation
of eleven (11) bridges. The bridge rehabilitations involve full
and partial deck replacements, repairs to stringers damaged by collisions;
replacement of sidewalks, railings and deck joints; replacement of overextended
rocker bearings, concrete repairs and numerous other incidental repairs.
Bayside's work involved the preparation of an in-depth structural survey
of all the bridges, preparation of preliminary design report outlining
the proposed repairs. Extensive maintenance of traffic plans were
developed to maintain traffic at all times during construction.
The following bridges were involved in this project.
A-2-29, Acton, route 111 over Route 2
A-2-35, Acton, Arlington Street over Route 2
A-2-36, Acton, Hayward Road over Route 2
B-18-1, Boxborough, Route 2 over Littleton Road
H-9-11, Harvard, Route 110 over Route 2
H-9-12, Harvard, Boxborough Road over Route 2
H-9-13, Harvard, Littleton Road over Route 2
H-9-14, Harvard, Oak Hill Road over Route 2
L-13-15, Littleton, Whitcomb Avenue over Route 2
L-13-17, Littleton, Route 2 over Foster Street
L-13-18, Littleton, Route 2 over Boston and Maine RR
Date Completed: 1993
 |
North Washington Street over Charles River,
Boston, MA
Bayside has been under contract with the City of Boston to design
the last two major repairs to this National Historic Register Bridge
located in Charlestown at the mouth of the Charles River. Currently,
Bayside is designing a new replacement sidewalk with improved railing
for pedestrian safety. The repairs also include repainting and
environmental mitigation and abatement for the removal of existing
leaded paint. Bayside Engineering also performed full-time resident
construction inspection services for the City of Boston, throughout
the construction period. |
Our previous (1993) North Washington Street bridges project involved major
steel repairs to the steel girders, floor beams and stringers. A new
concrete filled grating was installed on the swing span and the approach
to the swing span. The Alford Street project involved steel repairs
and deck repairs to the draw span superstructure, repairs to steel elements
within the mechanical room and minor repair work to the approach span deck
joints.
Rte I-95 over Merrimack River (Whittier Bridge),
Amesbury/Newburyport, MA
Bayside Engineering developed plans, specifications and construction cost
estimate for the replacement of failed nested roller bearings which support
the main trusses. A detailed method of jacking and temporarily supporting
the structure was devised to support bearing reactions, which ranged from
470 tons to 1655 tons, during the bearing replacement operations.
New state-of-the-art TFE Teflon/stainless steel bearings were used to
replace the roller bearings. Traffic management plans were prepared
to maintain a minimum of two lanes in each direction throughout the construction
phase. Date Completed: 1993
Relocated Depot Rd. (Main St.) over B&M
Railroad, Templeton, MA
This project involved the complete replacement of a functionally and structurally
deficient structure on an improved roadway alignment. The new bridge
is a two span continuous structure with horizontally curved steel girders.
A comprehensive 3-D analysis of the superstructure was performed using
finite element analysis software. The bridge was also analyzed and
designed in conformance with the latest AASHTO specifications for seismic
design of highway bridges. Date Completed: 1994
Some of the other bridge projects completed by Bayside in the past ten
years include:
Snowden Pond Culvert, Newton, MA (1998)
Route 38 over B&M Railroad, Tewksbury, MA
(1992)
Southbridge Street over Middle River, Worcester,
MA (1992)
Pike Avenue over Conrail, Attleboro, MA (1992)
Commonwealth Pier Viaduct, South Boston, MA (1991)
East Street over Big Bummett Brook, Grafton,
MA (1990)
Sumner Street over Conrail, Boston, MA (1990)
Summer Street over Conrail, South Boston, MA
(1990)
Dorothy Drive Bridge over MBTA Tracks, Randolph,
MA (1990)
Route I-93 over Salem Street Rotary, Medford
(1990)
Savin Hill Avenue over I-93 and MBTA Tracks,
Boston (1990)
Refer to our Home Page and Table
of Contents for additional information regarding our qualifications,
experience and Engineering and Architectural Services provided. Refer
to Projects
for representative designs completed by Bayside Engineering, Inc.
600 Unicorn Park Drive, 3rd
Floor
Woburn MA 01801
(781) 932-3201 l Fax (781)
932-3413
Introduction
/ Transportation Engineering
/ Civil Engineering
/ Bridge Engineering
Architectural Design
and Building Renovations / Projects
/ Representative Clients
/ Links / Home
|