|
The
rehabilitation involved six bridge structures, S-24-61-1, S-24-61-2, S-24-61A,
S-24-61B, S-24-83 and S-24-84. The rehabilitation was comprised of five
major components: bridge coping, expansion joints, bridge drainage, substructure
repairs and electrical system. The bridge coping was replaced to upgrade
the traffic safety of the bridge and included partial deck replacement.
The expansion joint repairs involved replacing the existing joints with new strip seal expansion joints and ride over joints. The bridge drainage rehabilitation included complete replacement of clearances and tie in to the existing street drainage system below the viaduct. Due to cracking and spalling of the concrete piers and abutments from
the leaking deck joints, substructure repairs were completed to prevent
any further deterioration. Replacement of the electrical system
was incorporated into the project due to the poor existing condition of
the system and involved replacing conduit, wire junction boxes and the
resetting of each light standard with new wiring, luminaries and bulbs.
Refer to Projects for additional designs completed by Bayside Engineering, Inc. 600 Unicorn Park Drive, 3rd Floor Woburn MA 01801 (781) 932-3201 l Fax (781) 932-3413
Introduction
/ Transportation Engineering
/ Civil Engineering
/ Bridge Engineering
|